How long it takes to get a building permit in Des Moines

Commercial and multi-family building permits issued in Des Moines this fall took a median of 49 days from application to issue. Residential building permits took a median of 6 days, and most plumbing, mechanical and electrical permits were issued the same day.

Based on 2,267 permits the City of Des Moines issued from October 1 through November 23, 2026, from the city's public permit system.

Source: dsmpermits.com analysis of City of Des Moines Citizen Self Service (EnerGov) public permit search records

Updated Nov 23, 2026.

Median wait by permit type

Calendar days from application to issue. The dark bar is the median; the light band shows the middle half of permits (25th to 75th percentile). Permit types with fewer than 10 permits in the window are left out.

Commercial and multi-family building

49 days median · 58 permits

Middle half: 27 days to 104 days. Issued the same day: 0%.

Sign

28 days median · 25 permits

Middle half: 19 days to 53 days. Issued the same day: 0%.

Sewer

23 days median · 12 permits

Middle half: 12 days to 39 days. Issued the same day: 8%.

Fire protection construction

20 days median · 43 permits

Middle half: 13 days to 31 days. Issued the same day: 0%.

Demolition

15 days median · 13 permits

Middle half: 2.6 days to 49 days. Issued the same day: 15%.

Grading

8 days median · 10 permits

Middle half: 1.8 days to 15 days. Issued the same day: 20%.

Fence

7.8 days median · 68 permits

Middle half: 5 days to 13 days. Issued the same day: 3%.

Residential building

6 days median · 219 permits

Middle half: 3 days to 13 days. Issued the same day: 5%.

Plumbing (other)

under 1 day median · 12 permits

Middle half: under 1 day to 2.8 days. Issued the same day: 67%.

Residential plumbing

under 1 day median · 505 permits

Three in four were issued within a day. Issued the same day: 86%.

Residential mechanical (HVAC)

under 1 day median · 327 permits

Three in four were issued within a day. Issued the same day: 94%.

Residential electrical

under 1 day median · 229 permits

Three in four were issued within a day. Issued the same day: 81%.

Commercial plumbing

under 1 day median · 60 permits

Three in four were issued within a day. Issued the same day: 88%.

Commercial electrical

under 1 day median · 57 permits

Three in four were issued within a day. Issued the same day: 93%.

Commercial mechanical (HVAC)

under 1 day median · 46 permits

Three in four were issued within a day. Issued the same day: 89%.

Right-of-way

under 1 day median · 421 permits

Three in four were issued within a day. Issued the same day: 89%.

Sidewalk and driveway approach

under 1 day median · 148 permits

Three in four were issued within a day. Issued the same day: 89%.

Compared with the same weeks of 2025

Building permits issued October 1 to November 23, 2025 versus the same window in 2026.

Commercial and multi-family building permits

2025
2026
Median wait
28 days
49 days
Middle half
8 to 60 days
27 to 104 days
Over 90 days
8
17
Permits issued
64
58
Total valuation
$28.1 million
$39.7 million

Residential building permits

2025
2026
Median wait
6.9 days
6 days
Middle half
3 to 14 days
3 to 13 days
Over 90 days
3
7
Permits issued
256
219
New homes, duplexes and townhomes
56
20
  • The median commercial wait rose from 28 days to 49 days, while 58 commercial permits were issued, compared with 64 a year earlier.
  • Published commercial valuation was $39.7 million, compared with $28.1 million in the same weeks of 2025 (up 41%).
  • Residential waits were about the same, at a median of 6 days. Permits for new homes, duplexes and townhomes fell from 56 to 20.

These are counts over about eight weeks, so a few large projects can move the numbers. Only building permits are compared; see the notes below.

Get the top 5 Des Moines metro permits every Monday, free

A short weekly email with the largest new building permits from the public record. Unsubscribe anytime.

How we measured

  • Wait is the number of calendar days from the application date to the issue date as recorded in the City of Des Moines EnerGov system. It includes time the application spent waiting on the applicant, such as plan corrections, not just city review.
  • Each permit is counted once, in the window it was issued. Applications that have not been issued yet are not included in either year.
  • The 2025 comparison covers building permits only (commercial, multi-family and residential). It was pulled from the same public search by permit number for permits numbered 2024 and 2025; permits issued in the 2025 window with older numbers, if any, are not included. Trade, right-of-way and other permit types were not compared year over year.
  • The 2026 window runs through November 23, 2026, the day the data was pulled, so the last day may be incomplete.
  • New housing counts are permits for new single-family homes, accessory housing units, duplexes and townhomes, not housing units.
  • Source: City of Des Moines Citizen Self Service (EnerGov) public permit search.

More Des Moines permit data

Cite or reuse this data

You are welcome to quote, chart or republish these figures. Please credit dsmpermits.com and link to this page.